muchen 牧辰

Sensitivity Analysis

Updated 2018-07-22

Sensitivity Analysis

The projected and actual cash flow might not be the same could be attributed to various uncertain variables. Such as (but not limited to): - Technological change - Change in competition in the industry - Macroeconomic change (inflation, unemployment, ecomoic growth, exchange rate) - Tarrifs, trade wars, etc. These will contribute to the inaccuracies of economic analysis.

Sensitivity Analysis is when we look at the change in output given some change in input. Similar to derivatives if you will (\(\frac{\Delta y}{\Delta x}\)). It is said to be sensitive if the output changes a lot with a small input.

The two types of sensitive analysises are break-even analysis and what-if analysis.

Break-Even Analysis

How much do we adjust our inputs such that our NPV or rate or return break-even

Break-even analysis is typically represented as a break-even chart that indicates clearly where two alternatives equal to each other.

Example: staged construction

We have two options (assuming 8% interest rate):

  1. Construct full-capacity building now for $140k
  2. Two stages: construct first stage now for $100k and second stage at time \(n\) for $120k

Notice that if we choose option 2 with \(n=0\), then the present worth of cost is $220k, not worth it compare to option 1.

However if we change the input \(n\) to a further date such that the cost discounted to present worth is less, then the present worth of cost of option 2 decreases:

\(n\) \((P/F, 8\%, n)\) PW of cost
5 0.6806 $182k
10 0.4632 $156k
15 0.3333 $140k
20 0.2145 $126k
30 0.0994 $112k

We see that the option 2 breaks-even with option 1 if we decide to construct the second stage at \(n=15\). Any \(n\) beyond that, we should choose option 2 over option 1.

Plotting \(n\) on the x-axis, we can see break-even point graphically:

<img src=”assets/image-20180722155806991.png” width=40%>

What-If Analysis

What if the revenue decreases by 5%, or what if cost to X increases by 12%, etc. How will the output change.

The what-if analysis shows how much a parameter must change to alter an economic decision and assess the inherent risk in a project. This is easily done in a spreadsheet by altering the variables.

Example:

Suppose the following base case: initial cost $300k, annual benefit $85k, salvage value $60k, lifetime of 6 years, and MARR of 14%.

The base case uses the standard, unmodified numbers for cost, benefits, lifetime, interest, etc.

Then we can set a few scenarios and setup a matrix where each base case property is increased or decreased by some percentage (in particular, -30%, -15%, +15%, and +30%). The modified values are in the table below.

  -30% -15% 0% (base case) 15% 30%
Initial cost $210,000 $255,000 $300,000 $345,000 $390,000
Annual benefit $59,500 $72,250 $85,000 $97,750 $110,500
Salvage value $42,000 $51,000 $60,000 $69,000 $78,000
Lifetime 4.20 5.10 6.00 6.90 7.80
Interest 10% 12% 14% 16% 18%

Then we can comptue the NPV for each of the modified parameters. Note that each NPV is assuming only one parameter is changing at a time.

  -30% -15% 0% (base case) 15% 30%
Initial cost $147,872 $102,872 $57,872 $12,872 $(32,128)
Annual benefit $(41,289) $8,291 $57,872 $107,452 $157,033
Salvage value $49,671 $53,772 $57,872 $61,972 $ 66,072
Lifetime $(8,431) $26,673 $57,872 $85,600 $110,244
Interest $106,617 $81,023 $57,872 $36,874 $17,779

We can notice how sensitive the NPV was to which input once we found the difference and color code the change.

image-20180722163750570

We see that initial cost and annual benefit changes the output the most, therefore they’re the most sensitive variables.


We can also do a break-even analysis for the two sensitive variables, initial cost and annual benefit, to see at which point the output, NPV is $0.

image-20180722165203845

For initial cost, the break even point is at approximately +20% of the base case. For annual benefit, the break even point is at approximately -17.5% of the base case.